Our Rutgers Tunnel work continues! Here's a snapshot of some work we've done so far: Replaced 9,270 linear feet (LF) of rails Installed 9,300 LF of temporary tunnel lighting Began replacing track ties, plates, and third rail equipment Learn more: https://t.co/52y8ADvf25 https://t.co/r0xmIxWHZ4 — PolitiTweet.org

Posted Feb. 19, 2021