Cyril Ramaphosa 🇿🇦 @CyrilRamaphosa

Eskom’s intention is to complete the remaining scope of works at Medupi and Kusile within the current project budgets approved by the Eskom Board. https://t.co/ncu27376sP — PolitiTweet.org

Posted Sept. 29, 2022

Preceded By

Profile Image

Cyril Ramaphosa 🇿🇦 @CyrilRamaphosa

The remaining cost to complete Kusile is R14 billion. 4 out of 6 Kusile units are in commercial operation and the current focus is on completing the commissioning of the remaining two units. https://t.co/ncu2736yDh — PolitiTweet.org

Posted Sept. 29, 2022

Followed By

Profile Image

Cyril Ramaphosa 🇿🇦 @CyrilRamaphosa

Eskom is making steady progress in developing & implementing effective technical solutions to the major plant defects at Medupi & Kusile Power Stations. As a result, the availability & reliability of the commissioned units at Medupi & Kusile is improving. https://t.co/ncu2736yDh — PolitiTweet.org

Posted Sept. 29, 2022